Installing module supports

5.2 Module installation, load redistribution and ballast

Installing the module
Fastening the modules on the row end
Fastening the module to the module joint
Insert the component into the base trough on one
side as shown and then click into the base trough.
The component may need to be screwed down,
depending on the wind load or if its position is
above long hole (MV 5).
Installation module support East-West regarding
MV4.
Prior to installation, the position (installation axis) of
the components must be determined on the base
trough.
Depending on the existing conditions on site,
installation using the installation and removal tool is
recommended.
Position the module on the base feet and then
place it on the module support set.
For notes regarding module installation for East-
West II, see MV 8.
Wire adjacent modules while installing them
Install the string cable first
Secure modules at the end of a row or at a break in
the row (light domes, fans, etc.) using the flat roof
end clamp (short side).
Push the clamping block of the module fastener
beneath the module, place the fastener on the
module and screw the drilling screw through the
bore hole.
Tightening torque max. 6 Nm.
The screw must not be overtightened!
Clamp on the short frame side.
Position the following module on the base foot or
module support. Determine the gap between the
modules (12 mm) by inserting the flat roof mid
clamp. Insert the module fasteners so that the
drilling screw is positioned in the bore hole on the
base foot or module support.
Tightening torque max. 6 Nm.
The screw must not be overtightened!
Clamp on the short frame side.