05-E4B, 05-E4BG SERIES, WSM
Nozzle Holder Assembly and Glow Plug
1. Remove the overflow pipe (1).
2. Remove the nozzle holder assemblies (4).
3. Remove the copper gasket (5) and heat seal (6).
4. Remove the lead (2) from the glow plugs (3).
5. Remove the glow plugs (3).
(When reassembling)
• Replace the copper gasket and heat seal with new one.
Overflow pipe retaining nut
(Serial No.: below BTZ999)
Overflow pipe retaining nut
(Serial No.: above BU0001)
Tightening torque
Nozzle holder assembly
Glow plug
(1) Overflow Pipe
(2) Lead
(3) Glow Plug
Nozzle Heat Seal Service Removal Procedure
IMPORTANT
• Use a plus (phillips head) screw driver (1) that has a
diameter which is bigger than the heat seal hole (Approx.
6 mm (1/4 in.)).
1. Drive screw driver (1) lightly into the heat seal hole.
2. Turn screw driver three or four times each way.
3. While turning the screw driver, slowly pull the heat seal (4) out
together with the injection nozzle gasket (3).
4. If the heat seal drops, repeat the above procedure.
(When reassembling)
• Heat seal and injection nozzle gasket must be changed when
the injection nozzle is removed for cleaning or for service.
(1) Plus Screw Driver
(2) Nozzle Holder
1-S31
ENGINE
20 to 24 N·m
2.0 to 2.5 kgf·m
15 to 18 lbf·ft
35 to 39 N·m
3.5 to 4.0 kgf·m
26 to 28 lbf·ft
49 to 68 N·m
5.0 to 7.0 kgf·m
37 to 50 lbf·ft
7.9 to 14 N·m
0.80 to 1.5 kgf·m
5.8 to 10 lbf·ft
(4) Nozzle Holder Assembly
(5) Copper Gasket
(6) Heat Seal
9Y1210784ENS0032US0
(3) Injection Nozzle Gasket
(4) Heat Seal
9Y1210784ENS0033US0