ELECTRIC WINCH INSTALLATION INSTRUCTIONS
ELECTRIC WINCH AND CABLE KIT INSTALLATION (40 - 45 FT CONVEYORS)
STEP 1:
If electric winch kit was ordered at the same time as the conveyor,
NOTICE
LOWER CONVEYOR UNTIL SLIDE IS AGAINST UPPER STOP,
steps 1 through 4 will not be necessary.
WHEN FULLY LOWERED WINCH CABLE SHOULD BE SLACK.
1. Lower conveyor until slide is against upper stop. When fully lowered winch cable
should be slack.
2. Once the cable is slack, remove cable clamps and cable from anchor.
STEP 2:
ONCE CABLE IS SLACK, REMOVE CABLE CLAMPS AND CABLE FROM ANCHOR.
3. Remove cotter pin, pulley pin and the pulley from the upper cross member.
Set pulley and pins aside for re-installation later.
Page 46
USC CONVEYORS
FOR 40FT AND 45FT CONVEYORS
STEP 3:
REMOVE COTTE
LAY PULLEY AN

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ts25Ts35

Table of Contents