Figure 4-10 Ac Cable Connection (1-Phase); Figure 4-11 Ac Cable Connection (3W+N+Pe); Figure 4-12 Ac Cable Connection In North American (3W+Pe) - Infinite Transtector DCIPS2B-S-00-B11 Installation Manual

Power supply system
Table of Contents

Advertisement

Installation Manual
| DCIPS2B-S-00-B11 Power Supply System
WARNING Used cable must be inserted into the terminal with as little insulation removed
as possible, so as to prevents any stranded conductor coming loose and touching any
other conductive parts. Tighten terminals securely with torque 1.5-1.8Nm.
1. Strip the AC input cable conductors to the correct length for connection to the terminals.
2. Route the AC input cable through the AC cable entry and connect the cable to the AC
terminals and tighten the screws to 1.5 - 1.8 Nm.
3. The mains input terminal blocks can be connected to:
1-phase 110VAC or 230VAC (Figure 4-10)
3-phase 110/190VAC or 230/400VAC (Figure 4-11).

Figure 4-10 AC Cable Connection (1-phase)

Recommended mains breaker:
1-phase 110VAC or 1-phase230VAC: UL listed, Single pole 3 x 50A C-characteristics.
30
+1 (208) 635-6400 | www.transtector.com
+1 (208) 635-6400 | www.transtector.com

Figure 4-11 AC Cable Connection (3W+N+PE)

Recommended mains breaker:
3-phase 230/400VAC: UL listed,Three pole 25A C-characteristics.
4. If the power system is to be connected to 208-240V North American 3-phase power
source, you have to first connect terminal L1 with N3, L2 with N1 and L3 with N2
(3W+PE). Refer to Figure 4-12 for details.

Figure 4-12 AC Cable Connection in North American (3W+PE)