Section 4
Starting up
IEC13000062 V1 EN-US
Figure 8:
7.
Close all open windows and start PCM600.
Setting up the PC to access the IED via a network
This task depends on the used LAN/WAN network.
4.6

Writing an application configuration to the IED

The application configuration is created using PCM600 and then written to the IED. Establish a
connection between PCM600 and the IED when an application configuration must be written to
the IED.
After writing an application configuration to the IED, the IED makes an application restart or a
complete IED restart, when necessary.
32
Select: Use the following IP address
The PC and IED must belong to the same subnetwork for this set-up to work.
Ensure that the IED includes the correct application configuration according to
project specifications.
The IED does not restart after reconfiguring IEC61850 (regardless of whether the
protocol is enabled or disabled).
© Copyright 2013 ABB. All rights reserved
IEC13000062-1-en.vsd
1MRK 504 136-UUS B
M11734-2 v5
Transformer protection RET650
Commissioning manual

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ret650 a01a 2w/1cbRet650 a05a 3w/1cbRet650 a07a oltcRelion 650 seriesRelion ret650

Table of Contents