Ensure that the IED receives IEC 61850-8-1 data on both ports A and B. In the local HMI navigate to
Main menu/Tests/Function status/Communication/PRP Status/LAN1–A / LAN1–B and check
that both signals LAN1-A and LAN1-B are shown as
the ports A or B. Verify that either signal LAN1-A or LAN1-B (depending on which connection that
was removed) are shown as
the removed connection after completed verification.
7.14

Exit test mode

The following procedure is used to return to normal operation.
1.
Navigate to the test mode folder.
2.
Change the
3.
Answer
Transformer protection RET650
Commissioning manual
Error and that the other signal is shown as Ok . Be sure to re-connect
Enable setting to Disable . Press the 'E' key and the left arrow key.
YES , press the 'E' key and exit the menus.
© Copyright 2013 ABB. All rights reserved
Ok . Remove the optical connection to one of
Section 7
Testing functionality
SEMOD53244-3 v4
85

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ret650 a01a 2w/1cbRet650 a05a 3w/1cbRet650 a07a oltcRelion 650 seriesRelion ret650

Table of Contents