GE TLE Scalable Series Installation Manual page 41

Table of Contents

Advertisement

Final units, first and last, of a RPA Parallel System
On the two boards P13/P14 – IM0022 – Bus Interface Board, of the first and last units of a Parallel
System, the switches SW1-1/2/3/4/5/6 MUST BE IN POSITION ON (see Fig. 4.9.2-2).
Intermediate units of a RPA Parallel System
On the two boards P13/P14 – IM0022 – Bus Interface Board, of the intermediate units of a Parallel
System, the switches SW1-1/2/3/4/5/6 MUST BE IN POSITION OFF (see Fig. 4.9.2-3).
Modifications reserved
GE_UPS_ISG_TLE_SUL_40K_M15_1US_V010.docx
B
J1
J2
J1
J1B/1
Fig. 4.9.2-2 Bus connection on first and last units
A
B
J1
J2
J1
J1B/2÷5
J1B/1
Fig. 4.9.2-3 Bus connection on intermediate units
Critical Power
A
J2
J1A/1
J2
J1A/1
J1A/2÷5
SW1
SW1
Installation Guide TLE Scalable Series 40 - 150 UL S1
Page 41/53

Advertisement

Table of Contents
loading

Table of Contents