Switched Live 1 Input Function:
The SL1 input can be configured as a Plant
function, if this is not required select 'None'.
Configure SL1
None
Enable
Configure SL1
None
Enable
Plant Setp. SL1
85 º C
Done
Plant Setp. SL1
85 º C
Done
Plant OpenTherm interface:
Plant OpenTherm control. If the boiler has
the requirement to use the OpenTherm
interface then select the connection type
used from the list. Otherwise set to 'None'.
Configure OpenTherm
None
On demand
Temperature demand
Configure OpenTherm
None
On demand
Temperature demand
Capacity demand
For On demand there is an associated
flow temperature setpoint:
OpenTherm Temp. Setpoint
60 º C
Done
OpenTherm Temp. Setpoint
60 º C
Done
Configure OpenTherm
On demand
Temperature demand
Capacity demand
Configure OpenTherm
Temperature demand
Capacity demand
42
SECTION 2 - INSTALLATION
Outside Sensor:
This sensor can be selected and used
for all demands to the boiler, if this is not
required select 'None':
Outside sensor available?
None
Yes
Outside sensor available?
None
Yes
Internal Time Clock:
Internal timeclock. A timeclock can be set
for the Plant, this will control all functions. It
can be set as a single or multiple day timer.
Use an internal time clock
No
Yes
Use an internal time clock
No
Yes
Internal Time Clock Single:
Single day timer is programmable for
each of the 7 days with 3 periods per day,
Monday through Sunday:
Time Clock
Single
Multiple
Single
Monday
Period 1 06:00-22:00
Period 2 00:00-00:00
Period 3 00:00-00:00 Done
Single
Tuesday
Period 1 06:00-22:00
Period 2 00:00-00:00
Period 3 00:00-00:00 Done
Single
Wednesday
Period 1 06:00-22:00
Period 2 00:00-00:00
Period 3 00:00-00:00 Done
Single
Thursday
Period 1 06:00-22:00
Period 2 00:00-00:00
Period 3 00:00-00:00 Done
Single
Friday
Period 1 06:00-22:00
Period 2 00:00-00:00
Period 3 00:00-00:00 Done
Single
Saturday
Period 1 06:00-22:00
Period 2 00:00-00:00
Period 3 00:00-00:00 Done
Single
Sunday
Period 1 06:00-22:00
Period 2 00:00-00:00
Period 3 00:00-00:00 Done
Single
Monday
Period 1 06:00-22:00
Period 2 00:00-00:00
Period 3 00:00-00:00 Done
Single
Monday
Period 1 06:00-22:00
Period 2 00:00-00:00
Period 3 00:00-00:00 Done
Once all days and times are set, select
'Done' to continue.
Installation & Servicing

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Heat 2 55Heat 2 45pHeat 2 55p

Table of Contents