To remove the power cable
1
Locate and identify the storage shelf that has the faulty power cable.
2
Do the following as applicable:
Disconnect the faulty power cable from the primary shelf.
Warning: Replace one power cable at a time only. If you need to remove both power cables
from the Primary Storage Shelf, ensure that there are no I/O operations on the appliance in
progress, and then turn off the Primary Shelf.
Disconnect the faulty power cable from the expansion shelf.
Warning: Replace one power cable at a time only. If both power cables must be removed at
the same time on the Expansion Storage Shelf, ensure that there are no I/O operations on
the appliance in progress and power off the Primary Shelf. After the Primary Shelf has powered
off (all displays are completely off), then turn off the Expansion Shelf.
To install the power cable
1
Verify that the AC power supply input for the storage shelves is within the range of 200 - 240 VAC
at 50/60 Hz, 9.13 - 10.95 A.
2
Remove the replacement power cable from any wrapping.
3
Do the following as applicable:
On the Primary Storage Shelf, connect a power cord to the power supply socket. Connect the
other end of each cord to the appropriate AC power source.
HSP #144: Storage Power Cable Replacement
4