3.2 Opening the Front Door

1 Turn the door key to unlock the door.
Pull up the rack handle, turn it in the direction of the arrow, and pull.
・Close the front door after fully securing the installed devices. Failure to do so may cause the devices to fall off the rack and be
damaged in the event of an earthquake.

3.3 Opening the Rear Door

1 Turn the door key to unlock the door.
Pull up the rack handle, turn it in the direction of the arrow, and pull.
Same as the Front Door operations.

3.4 Installing the Rack

Basic requirement : Before installing the rack, be sure to adjust the leveling feet as described below,
regardless of whether the rack is to be anchored to the building floor. Keep the rack level with the leveling
feet. Be sure to position the casters 1 to 2 mm above the floor. (Do not let the casters support the weight of
the rack.)
3.4.1 Installation methods for the rack to withstand earthquakes with an acceleration
of up to 2.5 m/s
(250 gal)
2
In these methods, the rack can be anchored or not anchored. Use one of the following methods depending
on your situation.
33