6. Installation
Tapping sleeves are recommended for installation of the pipe lines for the connection points of the measurement water to and
from MiniMaster, and for the dosage points for liquid acid and chlorine via hose pumps.
Hard PE hose is included that shall sit between MiniMaster, the prefilter and the pipe lines.
1. Install MiniMaster against a wall.
Install the included connections on MiniMaster,
see picture 2. Disconnect the brace (M), fold the
modules forward, screw the connections on
MiniMaster's inlet and outlet.
2. Assemble the prefilter, see instructions MA60-23.
NOTE: The top on the filter has an arrow
marking the flow direction.
3. Install the prefilter at a suitable location near
the MiniMaster.
4. Cut the included hose to suitable lengths and
connect them without sharp bends between the
MiniMaster and prefilter.
NOTE: When installing hose in hose couplings of an insert type:
Make a straight cut with a sharp knife in the hose, push in the
hose end approx. 10mm in the coupling, then pull the hose
backwards for secure locking.
5. Inlet A: Install a tapping sleeve after the sand filter on the
pressure side of the pool circulation pump (see A picture 3).
6. Outlet B: Install a tapping sleeve after the skimmer on the
suction side of the pool circulation pump (see B picture 3).
7. Cut the included hose to two suitable lengths, install hose
coupling to the respective tapping sleeve.
Use threaded seal at the connection of bushing 1/4"-1/2" to the
tapping sleeve/line pipe.
8. Connect the one hose to the prefilter and to inlet A.
9. Connect the other hose to the prefilter and to outlet B.
Alternative placement of outlet B: Guide the hose directly down
in the skimmer (C, picture 3) or to an equalization tank.
10. If dosage pumps are used for liquid chlorine and acid/alkali,
the dosing points shall be placed a MINIMUM of 500 mm
apart from each other, after other equipment for heating/other
disinfection.
Chlorine dosing is always placed last.
1. Skimmer
2. Main drain
3. Inlet
4. JetSwim
5. Light
6. Circulation pump pool
7. Filter
8. Heat exchanger
9. Check valve
10. Circulation pump heat
11. Boiler
12. Drain
13. Check valve (optional)
14. MiniMaster
15. Prefilter MiniMaster
16. Chlorine dosing
17. Chlorine
18. Acid/alkali dosing
19. Acid/alkali
Picture 1
M
Sid 5 MA60-16
1/4"
N
M
N = Measurement water tap
M = Measurement water outlet
12
ENGLISH
Picture 2.
Ball valve L2
1/4"
Ball valve L1
Picture 3