Sequence Of Installation And Commissioning Steps - Delta M70A 260 Installation And Operation Manual

Solar inverter
Table of Contents

Advertisement

7.2

Sequence of installation and commissioning steps

Step
Mounting the inverter
Grounding the inverter housing
Preparing electrical installation
Connecting the communication card
Installing the Sub-1G antenna
Installing the Wi-Fi module
Connecting the PC to the inverter
Connecting the grid (AC)
Connecting the solar modules (DC)
Completing electrical installation
Commissioning the inverter
Installation and Operation Manual for Solar Power Inverter M70A EU V2.0 EN 2020-08-03
Notice
Optional
Optional
Optional
This step is only necessary if
commissioning is carried out via
PC.
Sequence of installation and commissioning steps
Description in chapter
"7.3 Mounting the inverter", page 56
"7.4 Grounding the inverter housing", page 60
"7.5 Preparing electrical installation", page 62
"7.8 Connecting the communication card",
page 74
"7.8 Connecting the communication card",
page 74
"7.10 Installing the Wi-Fi module before commission-
ing (optional)", page 90
"7.8.7 Connecting a PC via RS485 (optional)",
page 86
"7.11 Connecting the grid (AC)", page 94
"7.12 Connecting the solar modules (DC)",
page 97
"7.13 Completing electrical installation", page 98
"8. Commissioning", page 101