De-Commissioning
7 De-Commissioning
- To avoid injuries, please follow the procedures to unload the inverter.
If it is necessary to put the device out of operation for maintenance or storage,
please follow the procedures below:
At inverter side:
1. Push Power button until BX6.3_AC shutdown, all LED indicators will show
"OFF" status.
2. Switch off AC power line breaker to disconnect from grid.
3. Wait for all LED indicator turning off.
4. Remove the AC and battery wiring.
5. Remove the communication module RS-485 connection from the computer
connection.
Now you may unload the inverter.