Benchmark 750-6000 with Edge [i]: Install-Startup Manual
SECTION 2 – INSTALLATION
WARNING!
When using the lifting tab and bar, ensure there is no load placed on the gas train or blower.
Attaching the Lifting Bar: BMK750-1000 Instructions
1. Remove the lifting bar from its shipping location at the rear of the unit (Figure 2-3a, View A).
Retain the two (2) hex head cap screws, hex nuts and flat washers.
2. Remove the top shroud from the boiler and locate the lifting tab at the top-rear of the heat
exchanger.
3. Attach the lifting bar to the heat exchanger lifting tab using the hardware removed in step 1
(Figure 2-3a, View B). The upper end of the lifting bar containing the oval cutout should be
positioned over the top of the heat exchanger as shown.
4. Using proper rigging equipment capable of lifting 1200 lbs. (544 kg), lift the boiler and
position it on the housekeeping pad.
5.
After the boiler is properly set on the pad, detach the lifting bar and replace the shroud on
the top of the unit, but retain the lifting bar for possible reuse at the installation site.
LIFTING
TAB
LIFTING
BAR IN
SHIPPING
POSITION
VIEW A - SHIPPING POSITION
Figure 2-3a: BMK750-1000 Boiler Lifting Provisions
OMM-144_B • GF-217 •
5/25/2020
LIFTING BAR
IN LIFTING
POSITION
VIEW B - LIFTING POSITION
Technical Support • (800) 526-0288 • Mon-Fri, 8 am - 5 pm EST