Chapter 2 - Installing The Controller Chassis And Shelves; Installations Of Controller Chassis In Two-Post Racks; Important Considerations For Successful Installations - NetApp AltaVault Cloud Integrated Storage 4.1 Installation And Service Manual

Table of Contents

Advertisement

Installing the controller chassis and
CHAPTER 2
shelves
This section provides information on installing an AltaVault Controller chassis and disk shelves in racks. It includes
the following sections:
"Installations of controller chassis in two-post racks" on page 11
"Installations of controller chassis in four-post racks" on page 14
"Installing disk shelves and disk drives" on page 18

Installations of controller chassis in two-post racks

Install the AltaVault controller chassis in either a flush-mount or mid-mount position in a two-post rack. Use the two-
post telco tray kit for both flush-mount and mid-mount installations. For mid- mount installations, use the mid-mount
telco kit.
The controllers require 6U of rack space in addition to 4U for each shelf.
If you are installing multiple AltaVault systems and disk shelves, install them from the bottom to the top of the rack
for the best stability. For consistency with AltaVault system stacking and for stability, position the controller above the
storage stack as the storage stack is heavier than the controller.
Caution: If you are installing the controller chassis without using the mechanical lift, at least three people must be available to lift
the controller chassis.

Important considerations for successful installations

If you are installing the controller chassis in an equipment rack or NetApp cabinet, use a 4-post system. Do not use a
Telco mounting kit in this cabinet. The cabinet has custom equipment mounting rails for this application.
Verify that your site meets the electrical and power requirements of the AltaVault controller using the steps described
in the procedure,
"Controller electrical requirements" on page
Verify that the rack is in its permanent position and the placement allows for adequate clearance for airflow and
hardware maintenance using the steps described in the procedure,
NetApp AltaVault Cloud Integrated Storage Installation and Service Guide for Physical Appliances
9.
"Site clearance requirements" on page
8.
11