Commissioning the SIPROCESS GA700

Procedure
Startup
Figure 8-1
1. Supply the device with power. Information on the power supply of the device is available
in the device-specific documentation → Table A-5 References 3 - Operating Instructions
(Page 99).
The boot process starts. The splash screen is initially visible on the device display.
2. Scan of basic settings:
The boot process is interrupted momentarily. Two successively displayed editing windows
prompt you to select the display language and to enter the date and time.
– Select one of the offered language options in the first editing window.
– Then set the date and time of day.
Once you have entered the requested information, the boot process continues.
Field device
Operating Instructions, 05/2015, A5E35640463-02
Product designation
Version of the device firmware
Progress bar
Splash screen
Note
Date / time settings
When the power is off, these settings for the date and time are stored on the device for
a period of approximately 14 days.
After putting the device back into operation, you will need to reset the date and time.
8.4 Commissioning the SIPROCESS GA700
Commissioning
75