Commissioning

IMPORTANT
The hygiene filter may be installed only after the hygiene maintenance ( 6) to avoid de-
stroying it.
Damage as the result of leaking water
Adhere to the following sequential order during commissioning:
Fill the water bath of the ice-bank ( 5.2)
Caution
Install the dummy plug ( 5.3)

5.1 Prerequisites

 Gas and water connection in accordance with chapter 4.
 Electrical connection in accordance with chapter 4.
 The water stop cock is closed.
 The valve on the carbonic acid bottle is closed.
 The shut-off valve after the gas pressure reducer is closed.
 The water dispenser is switched off.

5.2 Fill the ice-bank water bath

5.3 Installing the dummy plug

 Open the water stop cock.
 Fill the water bath to a level between MIN and MAX.
 Use a cable tie to fix the level indicator hose in place.
 Close the water stop cock.
 Insert the water connection hose into the "IN H
Before inserting the hose, spray the end of the hose with
EAUVATION N° 2.
 Pull out the mains plug.
 Unscrew the upper cover plate and remove it.
 Remove the bracket (1).
 Spray the inside of the filter head (3) with EAUVATION N° 2.
 Spray the dummy plug (4) with EAUVATION N° 2 and screw
into the filter head (3).
 Close the lever at the filter head (turn to the right).
 Install the bracket (1).
Commissioning
O" connection.
2
9