FusionModule2000 Smart Modular Data Center
Maintenance Guide
Step 3 Remove the cables from the eLight power supply.
Step 4 Remove the old eLight power supply from guide rails.
Step 5 Install the spare eLight power supply in the original position and connect the cables.
Step 6 Turn on the upstream fuse for the eLight power supply.
----End
5.4.26 Replacing a Smart U Space Manager
Impact on the System
The U space status of the equipment cannot be displayed during replacement.
Preparations
Figure 5-80 Smart U space manager installation diagram (main control box attached to the top of
the cabinet interior)
(1) Rack environment unit
(4) Asset detection strip (42 U detection point)
Issue 04 (2020-01-03)
Tools: ESD gloves, label, marker
Material: smart U space manager
Copyright © Huawei Technologies Co., Ltd.
(2) Fastener
(3) Main control box
(5) U space e-label (6) Server
5 Parts Replacement
119