Installation of ZB-S 2C3, CG100, CG 102 and CG 104 in the EBR-S-1800 electrical service room

Installation of ZB-S
2C3, CG100, CG 102
and CG 104 in the
EBR-S-1800 electri-
cal service room
1. Screw-fasten the
base for ELT rooms
40071360410 to the rear
wall of the room.
2. Align the system and
screw-fasten to the rear
wall of the room.
CAUTION
Holes must be pre-drilled
for fastening screws into
the fire protection material.
Drill hole depth: max. 25
mm, screw length: max.
25 mm.
3. Set up the technical
ventilation (see the
installation and ope-
rating instructions
ELECTRICAL SERVICE ROOM PRIORACK-Elt EBR)
4. Feed in the cables.
5. Connect the system in accordance with the CEAG
ZB-S instructions and carry out commissioning of the
system.
Installation of ZB-S 18C3, 10C3 and CG200 in
the EBR-S-1800 electrical service room
1. Align the system and screw-fasten to the rear wall of
the room.
CAUTION
Holes must be pre-drilled for fastening screws into the
fire protection material. Drill hole depth: max. 25 mm,
screw length: max. 25 mm.
2. Set up the technical ventilation (see the installation and
operating instructions ELECTRICAL SERVICE ROOM
PRIORACK-Elt EBR)
3. Feed in the cables.
4. Connect the system in accordance with the CEAG
ZB-S instructions and carry out commissioning of the
system.
Manual: ZB-S central battery system in electrical service rooms EBR-S 40071860238 (A) August 2014 www.ceag.de
ZB-S 2C3 in EBR-S-1800
CG100 in EBR-S-1800
ZB-S 18C3 and ZB-S 10C3 in
EBR-S-1800
CG102, 104 in EBR-S-1800
CG200 in EBR-S-1800