a. From the HPE OneView dashboard, select logical interconnects.
b. From logical interconnects, select the SAS logical interconnect.
c. View the alerts.
d. Select the missing drive enclosure alert.
e. Select the action to replace the missing drive enclosure.
f. From the replace missing drive enclosure pop-up screen, select the replacement storage module.
g. Click Yes, replace.
h. Monitor the task progress to verify that it has completed.
8. Add all the drives back into the same drive bay locations.
9. Power up the servers.
Installing the replacement HPE Synergy D3940 Storage Module
To install the replacement storage module, see "Installing an HPE Synergy D3940 Storage Module."
The drawer power LED will not illuminate green until a compute module containing one or more logical JBODs that are
assigned to the storage module is powered on.
Verifying proper operation
Check the following to verify that the module is working properly:
LEDs—See Front panel and LED definitions and check for healthy LED patterns.
•
•
HPE OneView—View system information, status alerts, device information, and confirm that the device status is Normal.
For more information on accessing and using HPE OneView, see the online help in the product or the HPE OneView Help
for HPE Synergy in the Hewlett Packard Enterprise information library (http://www.hpe.com/info/synergy-docs).
Replacing the I/O adapter
Removing the failed I/O adapter
Procedure
1. Open the release lever.
2. Remove the failed module from the frame interconnect bay.
Operations