Installing Your Analyzer

STEP 6. Start Up the Analyzer

STEP 6. Start Up the Analyzer
Install the instrument so that the detachable power cord is readily
CAUTION
identifiable and is easily reached by the operator. The detachable power cord
is the instrument disconnecting device. It disconnects the mains circuits from
the mains supply before other parts of the instrument. The front panel switch
is only a standby switch and is not a LINE switch. Alternatively, an
externally installed switch or circuit breaker (which is readily identifiable
and is easily reached by the operator) may be used as a disconnecting device.
1. Connect the AC power cable.