6 Commissioning

6.1 Commissioning an addressed detector line

6.1.1 Install flame detector on base for flame detector

Building Technologies
Fire Safety
This chapter explains how you set the parameter set and how you commission the
flame detector on the detector line. The commissioning process depends on
whether you are using an addressed detector line (FDnet/C-NET) or a collective
detector line.
See also
2 Commissioning an addressed detector line [
2 Commissioning on a collective detector line [
Sequence
1. Install flame detector on base for flame detector [
2. Set parameter set [
3. Run performance check [
You will find information on the individual steps in the specified chapters.
WARNING
Danger of falling
Bodily injury
When installing, use a secured ladder or work platform.
WARNING
Falling flame detector
Bodily injury
Never leave the flame detector hanging with the connection cable connected
to the base for flame detector.
1. Remove bridging connector (3) from base for flame detector.
2. Use the connection cable (2) to connect connections (4) in the base for flame
detector and on the flame detector.
3. Use four screws (1) to secure the flame detector to the base for flame detector.
a The flame detector is fitted.
Commissioning an addressed detector line
51]
51]
Commissioning
6
49]
52]
49]
49 | 66
007011_m_en_--
2018-06-28