Commissioning
6
Commissioning on a collective detector line

6.2.3 Run performance check

54 | 66
Building Technologies
Fire Safety
1. Remove bridging connector (3) from base for flame detector.
2. Use the connection cable (2) to connect connections (4) in the base for flame
detector and on the flame detector.
3. Use four screws (1) to secure the flame detector to the base for flame detector.
a The flame detector is fitted.
4
3
Figure 24: Mounting of flame detector on base for flame detector
1 Four screws for mounting
2 Connection cable
Use test lamp LE3 or a test fire to check the function of the flame detector.
The procedure control is described in the chapter 'Performance check [
See also
2 Performance check [
2
3 Bridging connector
4 Connection for connection cable
55]
1
55]'.
007011_m_en_--
2018-06-28