1. INTRODUCTION
(Figures 1 and 2)
The following instructions detail the steps for
terminating the CEELOK FAS-T Connector harness.
Refer to documents: Raychem RCPS-100-70
installation procedure for solder sleeve termination;
Application Specification 114-32025 for CEELOK
FAS-T High Speed Circular Connector System; and
Installation Procedure ELE-3COP-375 for braid
termination using a band strap adapter.
Dimensions in this instruction sheet are in
NOTE
millimeters [with inches in brackets]. Figures and
illustrations are for reference only and are not
i
drawn to scale.
Figure 2
1. Cut the cable to the desired length. Use an
appropriate cable cutter. Mark and strip
approximately 31.75 ±1.57 mm [1.25 ±.062 in.] of
cable jacket over the braid section. Refer to Figures
3 and 4.
Raychem is a trademark.
©2012 Tyco Electronics Corporation, a TE Connectivity Ltd. company
All Rights Reserved
*Trademark
TE Connectivity, TE connectivity (logo), and TE (logo) are trademarks. Other logos, product and/or Company names may be trademarks of their respective owners.
CEELOK FAS-T* Cable Harness
Manufacturing Guide
Figure 1
Cable O.D. Range:
5.59-10.16 mm [.220-.400 in.]
Maximum Conductor
Insulation Diameter
1.27 mm [.050 in.]
Cat6A Cable
TOOLING ASSISTANCE CENTER 1-800-722-1111
PRODUCT INFORMATION 1-800-522-6752
Receptacle
Connector
Plug Connector
Full Mate Indicator
Figure 3
Figure 4
2. Fold the braid back over the cable jacket and
remove foil wrap (if it exists) to expose the internal
conductors. Refer to Figure 5.
This controlled document is subject to change.
For latest revision and Regional Customer Service,
visit our website at www.te.com
Instruction Sheet
408-32046
02 APR 12 Rev A
Coupling Ring
Cat6A Cable
1 of 6

Advertisement

loading

Summary of Contents for TE Connectivity CEELOK FAS-T

  • Page 1 All Rights Reserved PRODUCT INFORMATION 1-800-522-6752 For latest revision and Regional Customer Service, *Trademark visit our website at www.te.com TE Connectivity, TE connectivity (logo), and TE (logo) are trademarks. Other logos, product and/or Company names may be trademarks of their respective owners.
  • Page 2 408-32046 For example, one pair should be loaded into cavities (1 and 2), another pair in cavities (3 and 4), another pair in cavities (5 and 6), and another pair in cavities (7 and 8). If it is difficult to seat the contacts by hand, the insertion tip of tool DHK696 can be used.
  • Page 3 408-32046 Figure 14 Figure 12 5. In cases where the contact needs to be removed from the connector after it is locked in place, the extraction tip of tool DHK696 is inserted into the circuit cavity to engage the latching clip tine to release it from the contact.
  • Page 4 408-32046 Trim the excess band by squeezing the cutoff handle until the band shears off. Remove the excess band from the tool by depressing the release handle and pulling it free. Trim the excess braid flush with the forward lip of the connector shell at the end of the knurled portion with side cutters.
  • Page 5 408-32046 Figure 22 Figure 25 7. Position the heat shrink boot over the terminated 8. EMI shielding can be maximized through an braid such that the lip end of the boot extends application of a braid sock termination to the beyond the raised rib on the connector shell.
  • Page 6: Revision Summary

    408-32046 2. REVISION SUMMARY Reflowed • Initial release of document Solder Ring Figure 28 Rev A 6 of 6...