Instructions For Start-Up; General; Cleaning The Pump; Cleaning Suction Line - Johnson Pump TG GS2-25 Instruction Manual

Internal gear pumps
Table of Contents

Advertisement

3.19 Instructions for start-up

3.19.1 General

The pump can be put into service when all arrangements described in chapter 3.18 Installation have
been made.
Prior to commissioning, responsible operators have to be fully informed on proper
operation of the pump/pump unit and the safety instructions. This instruction manual
must at all times be available to the personnel.
Prior to commissioning, the pump/pump unit must be checked for visible damage.
Damage or unexpected changes must be reported immediately to the plant operator.

3.19.2 Cleaning the pump

There may be residual mineral oil inside the pump deriving from the pump testing and the initially
lubricating of the bearing bushes. If these products are not acceptable for the pumped liquid, the
pump should be cleaned throughly. Proceed as described in section 3.21.2.8 Draining of fluid.

3.19.2.1 Cleaning suction line

When the TG pump is put into service for the first time, suction line must be cleaned thoroughly.
Do not use the pump. The TG pump is not meant to pump low viscosity liquids with impurities.

3.19.3 Venting and filling

To operate properly the pump should be vented and filled with the liquid to be pumped before the
initial start-up:
Unscrew the filling plug Bb and Be. Fill up the pump with the liquid to be pumped.
At the same time the pump will be vented.
Tighten the filling plugs.
When the TG pump is brought into service for the first time or in case new gaskets are mounted,
bolts that compress gaskets must after 3 - 4 days be tightened again
(for tightening torques see section 3.21.3.1).
Be
Be
A.0500.501 – IM-TGGS/05.01 EN (03/2013)
de
Ba
Bk
Bb
Bn
Ba
de
Bk
Filling up the pump