6.3.2

KNX S-mode commissioning

For KNX S-mode, the usual S-mode commissioning procedures apply for ETS3 or
ETS4. The HMI (push button and LED) conforms to the KNX standard. A short key
press sets the device into programming mode (cf. section 2.4).
6.3.3

KNX LTE-mode commissioning

VAV compact controllers, KNX LTE-mode controller and operating units are
connected to the power supply. Refresh, and then open the ACS790 device list.
⇓ variant 1 (with collected address labels)
1. Select a VAV compact controller from the device list by ID
(IDs are collected during mounting),
2. Double click the selected row to open the dialog box
"Address assignment",
or
⇓ variant 2
1. Set a VAV compact controller to addressing mode
(Push button on device ⇓ LED shines red)
2. In ACS790, click button "Programming mode" ⇓ Address assignment ⇓
enter physical address ⇓ click "Write"
⇓ Enter a physical address and short description for the selected VAV compact
controller,
⇓ Click "Write" to close dialog box,
⇓ Repeat steps for all VAV compact controllers for commissioning.
Continue: Further configuration with ACS790.
6.3.4

PL-Link commissioning

Multiple VAV compact controllers can be connected simultaneously to the power
supply or individually. For plug&play commissioning, the PL-Link capable
automation station must be preconfigured as described in section 6.2.3.
The PL-Link automation station is online.
The VAV compact controllers are not connected to the power supply.
⇓ Simultaneously connect all VAV compact controllers to the power supply (or
individually as applicable)
⇓ PL-Link automation station and VAV compact controllers execute registration
and address assignment. Configuration is uploaded from the automation
station to the VAV compact controllers.
⇓ Optional: Middle key press for connection test (>2 sec and <20 sec).
VAV compact controller KNX/PL-Link G..B181.1E/KN
CE1P3547en
2017-03-23