LCD Setting

After pressing and holding the ENTER button for 3 seconds, the unit will enter setting mode. Press "UP" or
"DOWN" button to select setting programs. And then, press "ENTER" button to confirm the selection or ESC
button to exit.
Setting Programs:
Program
00
Exit setting mode
Output source priority:
01
To configure load power
source priority
Maximum charging current:
To configure the total
charging current for solar
02
and utility chargers.
(Max. charging current =
utility charging current +
solar charging current)
Description
Selectable option
Escape
Solar first
Utility first (default)
SBU priority
10A
Solar energy provides power to the
loads as first priority.
If solar energy is not sufficient to
power all connected loads, battery
energy will supply power to the loads
at the same time.
Utility provides power to the loads
only when any one condition stated
below happens:
- Solar energy is not available
- Battery voltage drops to either low
DC warning voltage or the setting
point in program 12.
Utility will provide power to the loads
as first priority.
Solar and battery energy will provide
power to the loads only when utility
power is not available.
Solar energy provides power to the
loads as first priority.
If solar energy is not sufficient to
power all connected loads, battery
energy will supply power to the loads
at the same time.
Utility provides power to the loads
only when battery voltage drops to
either low DC warning voltage or the
setting point in program 12.