Install Ultraviolet Lamp

Important: Perform this procedure only after the quartz sleeve installation and leak-tests are completed
successfully.
1. Connect the UV lamp to the 4-point receptacle. If the lamp is not installed properly, lamp breakage will
occur.
2. Insert lamp into quartz sleeve through compression-nut pass-thru.
3. Install rubber boot over compression nut.
4. Connect unit power cable to power source.
5. Tighten the four (4) screws to secure the ballast box cover.
6. Prior to energizing the lamp, ensure that there is no water leaking from the quartz sleeve compression nuts.
Then, turn power ON.
Caution: Rapid successive cycling of the power to the ballast can cause premature failure of the unit.
7. Verify UV lamp operation from the viewport. Use the viewport to verify the proper operation of the UV lamp.
Allow one minute for the UV lamp to warm up prior to flowing water through the UV unit.

Mounting the Unit

Once the UV unit is assembled and tested successfully, it can be mounted onto its permanent operational location.
The unit must be mounted in a manner that will prevent excessive vibration and warping (which will damage the
quartz sleeve). Ensure that the following conditions are met when mounting/operating the unit:
• Release the pressure in the UV treatment chamber before breaking the compression nut seals.