Commissioning procedure – refer to diagram below
1
Check that both isolation valves are open.
2
Adjust balancing valve A to half open and balancing valve B to fully open.
3
Start up the heater and adjust balancing valve A to obtain a heater inlet temperature of
approximately 10°C greater than the system loop return temperature, (turning valve A in the open
direction will increase the heater inlet temperature and closing valve A will lower the heater inlet
temperature.
NOTE: The heater inlet should never be less than 41°C.
4
If the heater inlet temperature remains less than 10°C higher than the system loop return
temperature and valve A is fully open, leave valve A fully open and throttle valve B until the heater
inlet temperature rises to be 10°C higher than the system loop return temperature.
5
Main loop and heater temperatures should be checked regularly throughout the season to prevent
heater condensation. If the balancing valves are adjusted at the coldest loop temperature (typically
10°C) and the heater temperature to 41°C then the entire heating season should have a proper
41°C operation. The heater inlet temperature can be higher than 41°C without heater damage, but
operating at less than 41°C inlet can cause damage from condensation.