Position The Unit - Ecoer 2436 Installation Instructions Manual

Inverter split heat pump, up to 20 seer, 2-3-4-5ton capacity, r410a
Hide thumbs Also See for 2436:
Table of Contents

Advertisement

ESI Outdoor Unit Installation Instruction

3. Position the Unit

When mounting the unit on a roof, be sure the roof will
support the unit's weight obtained from nameplate.
Properly selected isolation is recommended to prevent
sound or vibration transmission to the building structure.
When installing the unit on a support pad, such as a
concrete slab, consider the following:
• The pad must be 1~2" larger than the unit on all sides.
• The pad must be separated from any structure.
• The pad must be level.
• The pad must be high enough above grade to allow for
drainage.
• The pad location must comply with National, State and
Local codes.
IMPORTANT NOTE:
These instructions are intended to provide a method to tie-down unit to cement slab as a securing
procedure for high wind areas. Check local codes for tie-down methods and protocols.
Refer to the unit dimensions.
DETAIL A
Manufacturer reserves the right to change specifications or designs without notice.
6/31
#7 × 3/8" self tapping screws
(Do not exceed 3/8" length.)
DETAIL A
1/4" × 1-1/2" hex washer head concrete screws
(3/16" pilot hole needed. Pilot hole should be1/4" deeper
than the fastener embedment.)
Figure 3-2 Fasten the outdoor unit
Figure 3-1 Position the unit on pad
Brackets:
2" width, 1/16" thickness,
height as required.
Available from distributor
or in market store.
www.ecoer.com
08.2018

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

4860

Table of Contents