6 - INSTALLATION AND ASSEMBLY OF BOILER

Instructions on how to install the structure of the LOGIKA boiler:
a. Positioning on the ground (lifting or slide).
b. Put the tank and boiler in the room where they are to be installed (but NOT in their definitive position).
c. Check and install any additional kits (automatic turbolators/automatic ash outlet).
d. Assembly of the right-hand side of the boiler.
e. Definitive installation with reference to the diagram showing the minimum requirements.
f. Assemble probe pipe 0 100 at boiler outlet.
g. Assemble the lambda probe and connect it to the boiler connector.
h. Connect the pressure gauge pipe to the pressure outlet.
a) Positioning on the ground (lifting or slide).
After unpacking the structure it is possible to move the boiler in two ways:
1) using the lifting hook on the boiler and a hoister.
WEIGHT ABOUT 500 KG
28 28