Finish Installation; Line Voltage Electrical Connection; Front Panel Installation - BeaconMedaes MEGA 2 Installation, Operation And Maintenance Instructions

Medical electronic gas alarm
Table of Contents

Advertisement

Finish Installation

Line Voltage Electrical Connection

1. Remove four nuts from plastic power
supply shield.
2. Remove plastic shield from power
supply. The plastic shield contains an
in-line fuse holder that is wired to a
two-pin plug on left side of power
supply assembly. Remove two-pin
plug from power supply.
3. The incoming line voltage hot and
neutral wires should be connected via
wire nuts to black (hot) and white
(neutral) wires of power supply two-pin
harness. Connect incoming ground
wire to alarm box green ground wire.
Refer to Figure 12.
4. Carefully position wires in bottom left
corner of alarm panel box. Reconnect
two-pin harness to power supply male
connector. Harness connector is
keyed to prevent incorrect orientation,
however, use care to ensure correct
pin alignment.
5. Reinstall plastic power supply shield
while making sure all high voltage
wires are contained within plastic
shield.
6. Secure plastic shield with four nuts.
Ground (green)
Fuse Holder
Line (black)
Neutral (white)
Figure 12: Line Voltage Connection

Front Panel Installation

1. Remove front panel assembly from
2. Remove two front panel hinge
3. Attach front panel hinge and lanyard to
Figure 13: Front Panel Hinge and Lanyard Screws
Power Supply
anti-static shipping bag.
mounting screws and lanyard mounting
screw from alarm panel back box
assembly (Figure 13).
alarm panel back box using screws
removed in step 2 as shown in Figure
14. Large (8-module) back boxes use
two lanyards, one on each side.
Lanyard screw
Figure 14: Attach Front Panel and Lanyard
Part No. 6-847684-00 Rev. D01
Hinge screws
27