Operational Control Sequence

1.1.1
Motor Operation
The motor runs on the 120V circuit of the dryer. Power is supplied into the RL2 relay.
Power is then fed through both the start and run windings on the motor. The centrifugal switch then disengages
the start winding once the motor has started.
In the motors neutral circuit there is an internal overload. The neutral circuit then runs through the door switch
and to the mains terminal block.
If reverse drum is selected, the motor terminals 3, 7, 8 and 9 are switched by the RL5 relay in order to change
the drum direction. The sequence is defined by 4 minutes in CCW, 40 seconds in CW direction and a pause of 5
seconds every direction change.
Fisher&Paykel
Operational control sequence
- 51 -

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

De7027p1usDg7027j1usDe7027p1caDe7027j1caDg7027p1us

Table of Contents