Typical workflow
Checking the refrigerant piping typically consists of the following
stages:
1
Checking for leaks in the refrigerant piping.
2
Performing vacuum drying to remove all moisture, air or
nitrogen from the refrigerant piping.
If there is a possibility of moisture being present in the refrigerant
piping (for example, water may have entered the piping), first carry
out the vacuum drying procedure below until all moisture has been
removed.
7.6.2
Precautions when checking the
refrigerant piping
INFORMATION
Also read the precautions and requirements in the
following chapters:
▪ General safety precautions
▪ Preparation
NOTICE
Use a 2-stage vacuum pump with a non-return valve that
can evacuate to a gauge pressure of −⁠ 1 00.7  kPa
(−⁠ 1 .007  bar)(5  Torr absolute). Make sure the pump oil
does not flow oppositely into the system while the pump is
not working.
NOTICE
Use this vacuum pump for R410A exclusively. Using the
same pump for other refrigerants may damage the pump
and the unit.
NOTICE
▪ Connect the vacuum pump to the service port of the
gas stop valve.
▪ Make sure that the gas stop valve and liquid stop valve
are firmly closed before performing the leak test or
vacuum drying.
7.6.3

To check for leaks

NOTICE
Do NOT exceed the unit's maximum working pressure (see
"PS High" on the unit name plate).
NOTICE
Make sure to use a recommended bubble test solution
from your wholesaler. Do not use soap water, which may
cause cracking of flare nuts (soap water may contain salt,
which absorbs moisture that will freeze when the piping
gets cold), and/or lead to corrosion of flared joints (soap
water may contain ammonia which causes a corrosive
effect between the brass flare nut and the copper flare).
1 Charge the system with nitrogen gas up to a gauge pressure of
at least 200  kPa (2  bar). It is recommended to pressurize to
3000 kPa (30 bar) in order to detect small leaks.
2 Check for leaks by applying the bubble test solution to all
connections.
3 Discharge all nitrogen gas.
7.6.4

To perform vacuum drying

Connect the vacuum pump and manifold as follows:
ERLQ004~008CA + EHBH/X04+08CB
Daikin Altherma – Low temperature split
4P384972-1B – 2017.04
a
d
h
b
c
j
e
f
g h i
a
Pressure meter
b
Gauge manifold
c
Low-pressure valve (Lo)
d
High-pressure valve (Hi)
e
Charging hoses
f
Vacuum pump
g
Service port
h
Valve lids
i
Gas stop valve
j
Liquid stop valve
1 Vacuum the system until the pressure on the manifold indicates
−0.1 MPa (−1 bar).
2 Leave as is for 4-5 minutes and check the pressure:
If the pressure...
Does not change
Increases
3 Evacuate for at least 2  hours to a pressure on the manifold of
−0.1 MPa (−1 bar).
4 After turning OFF the pump, check the pressure for at least
1 hour.
5 If you do NOT reach the target vacuum or cannot maintain the
vacuum for 1 hour, do the following:
▪ Check for leaks again.
▪ Perform vacuum drying again.
NOTICE
Be sure to open the gas stop valve after piping installation
and vacuuming. Running the system with the valve closed,
the compressor may break down.
INFORMATION
After opening the stop valve, it is possible that the pressure
in the refrigerant piping does NOT increase. This might be
caused by e.g. the closed state of the expansion valve in
the outdoor unit circuit, but does NOT present any problem
for correct operation of the unit.
7.7

Charging refrigerant

7.7.1

About charging refrigerant

The outdoor unit is factory charged with refrigerant, but in some
cases the following might be necessary:
What
Charging additional refrigerant
Completely recharging refrigerant Example:
7 Installation
Then...
There is no moisture in the
system. This procedure is
finished.
There is moisture in the
system. Go to the next step.
When
When the total liquid piping
length is more than specified
(see later).
▪ When relocating the system.
▪ After a leak.