Maintenance - Emerson FISHER FIELDVUE DLC3010 Instruction Manual

Digital level controller
Hide thumbs Also See for FISHER FIELDVUE DLC3010:
Table of Contents

Advertisement

Instruction Manual
D102748X012
Analog Output
(mA gauge) Indicates the current value for the analog output of the instrument being commanded by the firmware, in
milliamperes.
% Range
(span gauge) Indicates the current process variable in percent of span determined by the lower range value and the
upper range value.
Trends
Field Communicator
Service Tools > Trends (3-3)
D PV (time-base strip chart)
D SV (time-base strip chart)
D TV (time-base strip chart) (appears if RTD is installed)

Maintenance

Field Communicator
Service Tools > Maintenance (3-4)
Tests
LCD Test— only visible if LCD Configuration is installed
The meter activates all segments immediately after power‐up, during a digital level controller self‐test, or during a
master reset sent by a host supporting HART communications. You can also test the meter by selecting Turn Cells On
to turn on all display segments, including the analog output bar graph, or select Turn Cells Off to turn off all display
segments. When finished with the test, press OK to return the meter to normal display mode.
Loop Test— used to verify the controller output, the integrity of the loop, and the operations of any recorders or similar
devices installed in the loop. To initiate a loop test, perform the following procedure:
1. Connect a reference meter to the controller. To do so, either connect the meter to the test connections inside the
terminal box (see the Test Connections procedure) or connect the meter in the loop as shown in figure 2‐9.
2. Access Loop Test.
3. Select OK after you set the control loop to manual.
The Field Communicator displays the loop test menu.
4. Select a discreet milliamp level for the controller to output. At the "Choose analog output" prompt, select 4 mA,
20 mA, or Other to manually input a value between 4 and 20 milliamps.
5. Check the reference meter to verify that it reads the value you commanded the controller to output. If the readings
do not match, either the controller requires an output trim, or the meter is malfunctioning.
After completing the test procedure, the display returns to the loop test screen and allows you to choose another
output value or end the test.
Primary Calibration
The following contains a brief overview of the Full and Partial Calibration procedures. Refer to the Calibration section,
starting on page 58, for detailed calibration information.
DLC3010 Digital Level Controller
Service Tools
May 2018
77