Installation
When subbases have cavities, grout holes are provided to fill all spaces. After the grout has
hardened, permanently tighten the anchor bolts.
Figure 2: Leveling with wedges
When the grout has hardened and the anchor bolts are permanently secured, recheck level.
NOTICE: On large subbases/floorplates, shimming is recommended to be at 61cm | 24"
spacing.
Figure 3: Leveling with blocks and shims
Install pump, driver, and v-belt drive
Install and align the sheaves
Before installing the driver onto an overhead motor mount or side-by-side base, ensure that
Foundation requirements and baseplate mounting procedures sections are complete.
NOTICE:
Follow coupling manufacturer's installation and operation procedures.
6
Alignment procedures must be followed to prevent unintended contact of rotating parts.
Model JC Installation, Operation and Maintenance Instructions