Chapter 8: Testing The Complete Configuration - Avaya 03-300686 Installation And Connection

Mdf and telephones
Table of Contents

Advertisement

Chapter 8: Testing the complete configuration

This section provides tests for the complete configuration, including the control and signaling
networks and the telephones and consoles.
This section provides tests to:
review the status of the configuration.
test the duplication link to the servers (S8700-series only)
test the IP server interfaces, expansion interfaces, and TDM buses in the port networks.
test the telephones and other equipment.
See
LED indicators
Avaya Ethernet switch(es), uninterruptible power supplies (UPSs), and different circuit packs.
Note:
Circuit pack positions are usually given by cabinet, and slot. They may also be
Note:
given by port. The term "cabinet" refers to five G650 Media Gateways
TDM-cabled together in a rack, making up one port network. A port network is
defined as a group of media gateways connected together with one TDM bus.
Perform these tasks to test the configuration:
!
CAUTION:
To prevent unnecessary trouble tickets, do not enable the alarms (Alarm
CAUTION:
Origination feature) until all installation and administration procedures are
completed.
1.
Testing port network equipment
2.
Checking port network status for each media gateway
3.
Checking circuit pack configuration
4.
Testing the TN2312BP Internet Protocol Server Interface circuit pack
5.
Testing Expansion Interface circuit packs, if used
6.
Testing time division multiplexing bus for each port network
7.
Testing expansion interface exchange, if used, for each port network
8.
Testing telephones and other equipment
on page 147 for information regarding the LED status indicators for the
on page 136
on page 137
on page 139
on page 142