3. Operation the System
3.1 Switch on
System shall be turned on in the correct sequence to avoid any damage.
Step 1,Open cable box outer shell.
Step 2,Unlock then open Cable box inner
cover. Cable box locker can be opened
without tools
Step 3, Turn on the PV switch on the cable
box.
Step 4, Turn on the GRID switch.
Step 5, If backup load is applied, connect
it to Backup ports and turn on the Backup
switch; if not, then keep the Backup switch
off.
Note: the Backup switch is only used
1
when a backup load is applied.
2
Step 6
Step 7, Press button 1 on all the batteries,
and the indicator light 2 will be on.
Step 8
shell of Cable box.
Alpha ESS Co., Ltd.
22
Your Smart Energy
Turn on the Battery switch.
,
Close the inner cover and outer
,