Installation and commissioning flowchart

Identify the frame size of your drive: R5 or R6.
Plan the installation.
Check the ambient conditions, ratings, required
cooling air flow, input power connection, compatibility
of the motor, motor connection, and other technical
data.
Select the cables.
Unpack and check the units.
Check that all necessary optional modules and
equipment are present and correct.
Only intact units may be started up.
If the drive is about to be connected to an IT
(ungrounded) system, check that the drive is not
equipped with EMC filtering intended for grounded
systems.
Check the installation site.
Install the drive on a wall or in a cabinet.
Route the cables.
Phone: 800.894.0412 - Fax: 888.723.4773 - Web: www.clrwtr.com - Email: info@clrwtr.com
Task
See
Technical data / IEC data
or
Technical data
Planning the electrical installation
For compliance with the European Union EMC
Directive, see Technical data:
Option manual (if optional equipment is
included)
Mechanical installation:
Unpacking the
If the converter has been non-operational for
more than one year, the converter DC link
capacitors need to be reformed. Ask ABB for
instructions.
The ACS800-31/U31:
Type
installation:
IT (ungrounded)
Mechanical installation: Before installation
Technical data
Mechanical installation
Planning the electrical installation:
cables
For compliance with the European Union EMC
Directive, see Technical data:
21
NEMA data
CE marking.
unit.
code; Electrical
systems.
Routing the
CE marking.
About this manual