Establishing connection and verifying the IEC 61850 station communication
Section 4
4.1
4.2
Commissioning Manual
Establishing connection and verifying the
IEC 61850 station communication

Setting the station communication

To enable IEC 61850 station communication:
The IEC 61850-8-1 station communication functionality must be on in the local
HMI. Navigate to Main menu/Configuration/Communication/Station
communication/1:IEC61850-8-1 and set the Operation parameter to Enabled.
To enable GOOSE communication the Operation parameter for the corresponding
GOOSE function blocks (GOOSEBINRCV and GOOSEINTLKRCV) must be set
to Enabled in the application configuration.
To enable GOOSE communication via the front port the parameter GOOSE in
Main menu/Configuration/Communication/Station communication/
IEC61850-8-1 must be set to Front. To enable GOOSE communication via rear
port the parameter GOOSE must be set to LAN1.

Verifying the communication

Connect your PC to the substation network and ping the connected IED and the
Substation Master PC, to verify that the communication is working (up to the transport
layer).
The best way to verify the communication up to the application layer is to use protocol
analyzer ITT600 connected to the substation bus, and monitor the communication.