Basic Connections And Sizing - CD Automation Revo M 2PH User Manual

Hide thumbs Also See for Revo M 2PH:
Table of Contents

Advertisement

CD Automation srl

7 Basic Connections and sizing

Star wiring with resistive load (control on two phases with REVO M-2PH)
P
I
1,
73
V
V = Nominal voltage of the load
I = Nominal current of the load
P = Nominal power of the load
Delta wiring with resistive load (control on two phases with REVO M-2PH)
P
I
1,
73
V
V = Nominal voltage of the load
I = Nominal current of the load
P = Nominal power of the load
CD-Eng-REVO-M-2PH-30-40A-Thyristors-Units
REVO M
11
User's Manual
I
V
I
V

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Revo M 2PH and is the answer not in the manual?

Table of Contents