Plugging on an operator panel
Procedure
To plug an Operator Panel on the Control Unit, proceed as follows:
1. Locate the lower edge of the Operator Panel into the matching
recess of the Control Unit.
2. Press the Operator Panel onto the inverter until you hear the latching
mechanism engage.
You have plugged an operator panel onto the Control Unit.
The operator panel is ready for operation when you connect the inverter
to the power supply.
Mounting the operator panel or dummy cover on the IP55 Power Module
Note
For degree of protection IP55 and UL-type 12, either an operator panel has to be inserted or
the dummy cover.
The Basic Operator Panel (BOP-2) and the Intelligent Operator Panel (IOP) are available as
operator panels.
A dummy cover is plugged on and removed just the same as an operator panel.
CU230P-2 Control Units
Compact Operating Instructions, 01/2016, A5E37058917B AA
3.1 Plugging the Control Unit onto the Power Module
Plugging on an operator panel: Press the operator
panel onto the inverter as shown until you hear it
engage.
Removing an operator panel: Using a suitable
screwdriver, press the release element down-
wards.