Section 2: Installation

2.1

Unpacking and Inspection

Inspect the outside of the carton for any damage. If damage is detected, contact the carrier
immediately. Inspect the instrument and hardware. Make sure all items in the packing list are
present and in good condition. Notify the factory if any part is missing.
2.2

Mechanical Installation

1.
2.
3.
Note: The flow cell must drain immediately to open atmosphere. Do not use a long or convoluted
drain line.
Figure 2-1: Dimensional Drawing for Rosemount 3200HP
Installation
Refer to
Figure 2-1
for dimensions of the mounting plate and the positions and diameter
of the mounting holes.
Remove the bag containing the diffuser plate from the flow cell. Place the diffuser plate
flat in the bottom of the flow cell. See
Connect the sample and drain lines to the flow cell. Process connections are ¼ inch FNPT.
Figure
2-2. Do not install the sensor yet.
Installation
April 2017
3