5.1 OVERVIEW
For Wye-connected VTs, the secondary nominal voltage (1 pu) would be:
Many settings are common to most elements and are discussed below:
FUNCTION setting: This setting programs the element to be operational when selected as "Enabled". The factory
default is "Disabled". Once programmed to "Enabled", any element associated with the Function becomes active and
all options become available.
NAME setting: This setting is used to uniquely identify the element.
SOURCE setting: This setting is used to select the parameter or set of parameters to be monitored.
PICKUP setting: For simple elements, this setting is used to program the level of the measured parameter above or
below which the pickup state is established. In more complex elements, a set of settings may be provided to define the
range of the measured parameters which will cause the element to pickup.
PICKUP DELAY setting: This setting sets a time-delay-on-pickup, or on-delay, for the duration between the Pickup
and Operate output states.
RESET DELAY setting: This setting is used to set a time-delay-on-dropout, or off-delay, for the duration between the
Operate output state and the return to logic 0 after the input transits outside the defined pickup range.
BLOCK setting: The default output operand state of all comparators is a logic 0 or "flag not set". The comparator
remains in this default state until a logic 1 is asserted at the RUN input, allowing the test to be performed. If the RUN
5
input changes to logic 0 at any time, the comparator returns to the default state. The RUN input is used to supervise
the comparator. The BLOCK input is used as one of the inputs to RUN control.
TARGET setting: This setting is used to define the operation of an element target message. When set to Disabled, no
target message or illumination of a faceplate LED indicator is issued upon operation of the element. When set to Self-
Reset, the target message and LED indication follow the Operate state of the element, and self-resets once the oper-
ate element condition clears. When set to Latched, the target message and LED indication will remain visible after the
element output returns to logic 0 - until a RESET command is received by the relay.
EVENTS setting: This setting is used to control whether the Pickup, Dropout or Operate states are recorded by the
event recorder. When set to Disabled, element pickup, dropout or operate are not recorded as events. When set to
Enabled, events are created for:
(Element) PKP (pickup)
(Element) DPO (dropout)
(Element) OP (operate)
The DPO event is created when the measure and decide comparator output transits from the pickup state (logic 1) to
the dropout state (logic 0). This could happen when the element is in the operate state if the reset delay time is not '0'.
a) BACKGROUND
The T35 may be used on systems with breaker-and-a-half or ring bus configurations. In these applications, each of the two
three-phase sets of individual phase currents (one associated with each breaker) can be used as an input to a breaker fail-
ure element. The sum of both breaker phase currents and 3I_0 residual currents may be required for the circuit relaying
and metering functions. For a three-winding transformer application, it may be required to calculate watts and vars for each
of three windings, using voltage from different sets of VTs. These requirements can be satisfied with a single UR, equipped
with sufficient CT and VT input channels, by selecting the parameter to measure. A mechanism is provided to specify the
AC parameter (or group of parameters) used as the input to protection/control comparators and some metering elements.
Selection of the parameter(s) to measure is partially performed by the design of a measuring element or protection/control
comparator by identifying the type of parameter (fundamental frequency phasor, harmonic phasor, symmetrical component,
total waveform RMS magnitude, phase-phase or phase-ground voltage, etc.) to measure. The user completes the process
5-4
13800
×
--------------- -
120
115 V
=
14400
13800
120
--------------- -
×
--------- -
66.4 V
=
14400
3
T35 Transformer Management Relay
5 SETTINGS

5.1.3 INTRODUCTION TO AC SOURCES

(EQ 5.1)
(EQ 5.2)
GE Multilin