this feature are given in Figure 21. See "Overhead cable management (top exit)" on
page 143 for critical safety, service, and installation considerations for this feature.
Figure 21. Measurements for DS8000 placement with top exit bracket feature present
The following notes provide information about the labeled components in
Figure 21:
Meeting floor load requirements
It is important for your location to meet floor load requirements.
Use the following steps to ensure that your location meets the floor load
requirements and to determine the weight distribution area required for the floor
load:
148
Introduction and Planning Guide
33 (1.3)
2
1 Top exist bracket for Fibre cables
2 Top exit cable channel bracket
Rear
585 (23.0)
209 (8.2)
Front
61 (2.4)
1