2 Commissioning

Switch on the boiler. Activate the main switch in the installation.
Commissioning cycle
Screen display:
- F XX: Software version
- P XX: Parameter version
The current operating status is shown on the display:
Heating only:
1: Fan ON
2: Boiler is igniting
3: Operation: Heating mode
Heating only: condition satisfactory
1: Post-ventilation
6: Pump operation (Heating mode)
0: Stand-by
2.1
Display
No display:
- Check that the boiler is switched on (230 V),
- Check the electrical connections,
- Check the fuse (F2 = 2 AT, 230 V).
Breakdown codes:
- The symbol
flashes,
- A malfunction code indicates the nature of the breakdown (for
example: E10),
- Correct the error if possible,
- Press key
for 2 seconds: The boiler restarts.
After an E1, E2, E7, E10 or E13 error, the 3-minute air venting
cycle will take place before the boiler starts up.
2.2
Parameter display (See "Control panel")
2.3
Boiler setting
"User" settings
Parameters P1 to P6 can be modified by the user in order to meet
central heating and DHW comfort needs.
"Installer" settings
Parameters P17 to dF must only be modified by a qualified
professional.
08/06/06 - 300008460-001-B
The boiler will begin an automatic venting-programm (which
lasts approx. 3 minutes) and will do this every time the power
supply is isolated. The version numbers are displayed
alternately.
production of domestic hot water:
1: Fan ON
2: Boiler is igniting
4: Operation: Domestic hot water mode
production of domestic hot water: condition satisfactory
1: Post-ventilation
7: Pump operation (Domestic hot water mode)
0: Stand-by
MCR 24, 24/28 MI, 30/35 MI, 34/39 MI
39

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Mcr 24/28 miMcr 30/35 miMcr 34/39 mi

Table of Contents