Connect the drainage tube of the unit to the collection tray
(U4) of the humidifier.
Connect the drainage tube of the humidifier (U7) to the drains
of the building using a rubber or plastic tube, which is resistant
to high temperatures (minimum 100 °C) with an internal
diameter of 22 mm.
U4
IThe external drainage tube must be siphoned to avoid
unpleasant odours and an overflow of the water from the tray
of the humidifier.
Maintain a minimum slope of 1% downstream of the siphon.
Drain
Siphon
Maintain a minimum slope of 1% downstream of the siphon.
Once the connections have been made, pour water into the
condensate collection tray of the Amico unit and in the con-
densate collection tray of the humidifier until both siphons
are full.

Hydraulic connections

For all hydraulic connections (except for the condensate drain)
it is recommended to use the following:
-
flexible hoses to avoid the transmission of vibrations and
to allow the unit to be moved;
-
three piece joints near the connections;
-
shut off valves to isolate the unit from the water circuit: if
possible, use full sphere valves to minimise the pressure
drop.
Check that the chilled water pipe sizes and the circulating
pump characteristics are adequate: an insufficient water
flow affects the performance of the unit.
Check that the water flow directions are respected.
Insulate all of the chilled water pipes with closed cell insulating
material (e.g.: Armaflex or equivalent) to avoid condensation;
the insulation must allow accessibility to the valves and three
piece joints.
Check that the hydraulic circuits (both chilled and hot water)
are fed with a maximum water pressure of 6 bar: to this
purpose the installer must install a safety valve in the hydraulic
with a set point of not more than 6 bar.
The minimum and maximum water temperatures inside the
unit (for the chilled water circuit and the post- heating with
hot water) are: 5°C ÷ 90°C.
The maximum amount of ethylene glycol is 50%.
42

Filling the hydraulic circuit

U7

Filling the primary circuit

Open the drain valve of the primary circuit and regulate the
pressure switch to 5 bar;
bleed the air from the circuits;
turn on the primary circulation pumps;
clean the circuits leaving the pumps on; check for any loss
from the primary circuits.

Filling the hydraulic circuits of the conditioners

Minimum slope
%
Open the shut off valves of the conditioner;
Open the bleeding valve (on the upper part of the cooling
coil) and wait for the water to come out.
WARNING! The water used to fill the hydraulic
circuit must be filtered.
WARNING! Filling the hydraulic circuit must only
be carried out exclusively by a qualified
hydraulic technician.
WARNING! Before carrying out any type of
intervention, disconnect the power supply.
WARNING! The primary circuits must be
equipped with mechanical filters.
WARNING! Check that all of the shut off valves
are closed.
WARNING! Clean the primary circuits before
filling the conditioners.
WARNING! Check that all of the bleeding valves
on the conditioners are closed.