Commissioning - Siemens SIMEAS P 7KG7750 Operating Instructions Manual

Power meter
Hide thumbs Also See for SIMEAS P 7KG7750:
Table of Contents

Advertisement

Available languages

Available languages

2.17

Commissioning

The ratings and information on the nameplate should be
checked prior to connecting the power supply voltage. In
particular, power supply voltage ratings, as well as input
voltage and current ratings should be verified. A warm-up
period of 15 minutes is required before the device will per-
form within specified accuracy limits.
The battery serves to buffer the memory and the real-time
clock of the SIMEAS P. The battery is included in the deliv-
ery scope. The battery is delivered in an isolated state.
Remove the cover of the battery slot on the top of the de-
vice and remove the battery and the isolation. Insert the
battery without isolation according to the polarity printed on
the top of the device (marking shield) and replace the bat-
tery cover.
If the battery voltage is low a blinking battery symbol occurs
in status line of the display. Please change the battery in
this case as described before. Use an isolated tool to re-
move the battery from the device to avoid a short-circuit!
WARNING!
Servicing of the battery circuit and replacing of the battery
must be performed by qualified personnel only.
Battery may explode if mistreated: Do not reverse the polarity!
Do not disassemble! Do not completely discharge! Do not
throw the battery into a fire!
The supplied battery contains lithium. Do not throw the bat-
tery into the trash! It must be disposed of in accordance with
the applicable regulations!