Statement 8:
CAUTION:
Never remove the cover on a power supply or any part that has the following
label attached.
Hazardous voltage, current, and energy levels are present inside any
component that has this label attached. There are no serviceable parts inside
these components. If you suspect a problem with one of these parts, contact
a service technician.
1. Ensure that the ac power switch is off on the power supply that you are
2. Install the power supply in the storage server, as follows:
3. Wrap the strain-relief clamp around the power cord approximately 20 cm (8 in.)
4. Attach the power-supply nut and tighten it securely.
5. Connect the power cord to the AC power connector. See Figure 62.
Figure 62. Connecting the power cord to the AC power connector
6. Plug the power cord into a properly grounded electrical outlet.
7. Turn on the power-supply switch.
8. Make sure that the green Power LED on the new power-supply CRU is on and
82
IBM TotalStorage FAStT100 Storage Server: Installation, User's, and Maintenance Guide
installing.
a. Slide the power supply into the storage server. Make sure that the lever is
pulled straight out as you slide the power supply into the storage server.
b. Close the lever until the pull-ring latch locks in place. Make sure that the
lever locks into place in the storage-server chassis.
from the power-supply connection end.
Lever
AC power
Strain-relief
-
AC power
connector
clamp
switch
the amber Fault LED is off.
v If the Power LED is off, the power-supply CRU might not be installed
correctly. Remove it and then reinstall it.