Pre-Installation

The following activities will need to be carried out, before installation and
commissioning of the FAU at the subscriber's site:

• Pre-installation Planning.

• Preparatory Field Engineering Work.
• Preparation and configuration of the FAU at the Engineering Depot.
Pre-Installation Planning
Pre-installation planning activities may include:
• Survey of subscriber location, address and mains voltage.
• Identify mounting location for FAU and type of pole/mast/wall fixing.
• Confirm position of the FAU is acceptable with customer/service provider.
• Identify position of possible interfering transmissions. This could be fixed
• Identify position for FAU safety earthing system.
• Identify location for 48 V DC power supply.
• Identify position of any cross-connect unit/junction box and telephone socket.
• Determine and gain appropriate planning approval for the following cable
service microwave transmissions, radar pulses or a cellular base station.
routes:
FAU - subscribers premises.
FAU - power supply.
FAU Installation Handbook
Typical FAU installation
3